Parts / dock-funnelactive
Fig. — dock-guide-quarter-r0.2.0.stl
component · fabricated · printed
High-dock alignment funnel
1 each required in the current BOM build.
BOM, procurement and usage detailsWarning · 2
- Fabrication status is concept-unvalidated; fit, materials and physical acceptance still need committed evidence.
- in-house-fabrication-dock-capture-set: Qualification is baseline-selected; the recorded selection is not engineering approval.
Issues · 4
- dock-funnel: Print material cost is estimated from solid CAD volume; supports, waste, shipping, tax adjustment, energy, machine time and labour are unresolved.
- in-house-fabrication-dock-capture-set: Price and availability observation date is unknown; quote capture time is not verification time.
- in-house-fabrication-dock-capture-set: Price is unknown.
- in-house-fabrication-hr: Shipping observation date is unknown; quote capture time is not verification time.
- Model
- dock-guide-quarter
- Role
- fabrication
- Status
- Concept · unvalidated
- Revision
- 0.2.0
- Document
- Geometry and assumptions
CAD release
Requirements
- Four quadrants form a nominal 275 mm mouth and 60 mm throat with edge-open 18 mm line slots; tabs attach through the support platform to the locator flange. Slots do not establish surveyed line routing.
DOCK-IF-01 bench-development kit, not accepted for suspended installation. Bought hardware is counted separately.