Prototype and commissioning

Principle

ARBI progresses by reducing uncertainty at the smallest practical scale. A later integrated demonstration does not erase missing component evidence. Each phase records the exact hardware, source revision, configuration, conditions, instruments, results, failures, and reviewer.

Phase 1 — bench winch

  • Acquire the selected closed-loop stepper kit plus representative Dyneema, shaft, bearings, coupling, and controller parts.
  • Print one complete winch revision.
  • Characterize direct-drive force, speed, acceleration, repeatability, holding, heat, and faults.
  • Exercise one-layer winding across the full intended drum width.
  • Measure effective radius/length mapping, reversal error, line tracking, and maximum useful tension.
  • Test home/reference and bounded recovery after lost position.
  • Inspect guards, retention, fasteners, printed creep, bearing load, and failure modes.

Exit evidence: an approved mechanical revision and measured operating envelope, not merely visible motion.

Phase 2 — powered line

  • Build a representative hybrid line with two conductors mechanically slack relative to Dyneema.
  • Build the rotating slip-ring and stationary/rotating strain relief.
  • Run repeated full winding/unwinding cycles under representative bend and tension.
  • Inspect conductor fatigue, abrasion, insulation, local stiffness, temperature, and effect on line tracking.
  • Measure voltage at maximum extension under the worst expected Pi/camera/servo/Wi-Fi load.
  • Exercise open/short/contact-intermittency and branch-protection responses under a controlled procedure.

Exit evidence: justified working current/voltage, construction, cycle life or replacement interval, and safe fault behavior.

Phase 3 — camera pod and dock

  • Print and assemble the current compact camera-pod configuration using its selected kit and revisions. Do not add the archived docking stud or historical printed alternatives to that kit.
  • Develop the structural docking attachment with the dock interface package; exercise a secured dummy-pod capture/release fixture before real pod integration using the bench plan.
  • Install Pi 3A+, selected converter/capacitor, Camera Module 3, and two selected micro servos.
  • Weigh the complete pod and record center of gravity.
  • Calibrate pan to approximately ±90 degrees and tilt from straight down toward approximately 70 degrees sideways, bounded by safe limits.
  • Verify stable pod voltage under simultaneous worst expected loads.
  • Implement and measure stop → gimbal → settle → autofocus → capture.
  • Test Wi-Fi transfer, local caching, reset, and command interruption.
  • Exercise funnel capture, latch, dock confirmation, release, shelter, drainage, and maintenance access.

Exit evidence: accepted mass, power stability, gimbal/camera performance, and dock capture/recovery envelope.

Phase 4 — small four-cable frame

  • Build an approximately 4 × 2 m controlled test rectangle.
  • Install four winches, representative pulleys/lines, pod, and a test dock or safe restraint.
  • Implement synchronized inverse kinematics and smooth trajectories.
  • Validate positive-tension strategy, workspace limits, homing, stopping, and representative fault responses.
  • Install fiducials and capture repeatable images at known positions.
  • Record motion, line, motor, pod, and image data for simulator comparison.

Exit evidence: repeatable integrated operation in a controlled exclusion zone with known residual risks and bounded recovery.

Phase 5 — full outdoor installation

  • Survey the site and update the structural, electrical, environmental, privacy, and maintenance plans.
  • Install and inspect four posts and guy anchors.
  • Pull-test and resurvey corner structures.
  • Install and electrically test cabinet and field distribution.
  • Install winches, four lines, pod, dock, and fiducials.
  • Load the as-built coordinate/configuration revision.
  • Calibrate anchors, line references, safe workspace, bed/plant targets, gimbal, camera, dock, and vision processing.
  • Commission in stages with exclusion zones, reduced limits, fault injections, weather checks, and inspections.
  • Integrate cloud requests only after local operation is accepted.

Exit evidence: complete as-built record, accepted safety case, qualified reviews, operating envelope, inspection schedule, and release tag.

Local safety and update gates

ADR-0006 and the local safety interface matrix define required functions and evidence owners. These gates govern authority for the named rig/target/configuration. No gate is passed merely by merging requirements, changing a capability flag or completing a GitHub issue.

Stage Entry, scope and exit requirements
Source/design and simulation Requirements and fixtures may use simulated or unavailable inputs. Review interface semantics and fault scenarios; label every result as source/model evidence. No physical actuation or field activation authority follows.
Secured isolated bench/HIL Explicit authorization under a reviewed test procedure for the exact target, wiring, fixture and configuration. Disconnect operational actuator loads or use secured controlled substitutes/restraint; define reduced travel/speed/force/time, exclusion zone, accessible isolation, initial output states and stop conditions. Actuation/flashing may produce B evidence before installed gates pass. Actual target timing and electrical response are measured; substitute-input tests cannot validate absent sensors or loaded restraint.
Secured loaded frame Accept relevant component/interface B evidence, rig structural/electrical hazards, independent stop path, restraint, calibrated force/position/clearance measurements and test-specific fault/recovery procedure before applying load. Measure the LS fault matrix under reduced limits and controlled access. The test rig's acceptance does not enable unattended or installed operation.
Installed operational actuation Disabled until the as-built installation has required B/F/I evidence, approved local configuration/calibration, independent protections, measured line tension/clearance, power-loss response, local weather/access policy and applicable Q reviews. Missing mandatory observations or limits block the affected capability.
Loaded/installed motion-controller updates Disabled until that stage's target-specific LS-18 restraint/clearance evidence and LS-03/08/12/16/17 reset/isolation/recovery prerequisites are accepted. Parked, zero commanded speed or a signed artifact is insufficient. Conflicting motion/manual/maintenance work is locked out; interrupted update/reset cannot automatically restore commands. Edge/pod restarts also need their own reviewed outage/recovery procedure.
Public operation and return to service Release evidence index, qualified acceptance, residual-risk/inspection/recovery procedures and deliberate local authorization for the released installation. Material hardware/firmware/configuration/calibration changes invalidate affected evidence and require retesting before restoring authority.

All physical gates above are currently unverified. Source checks, simulator assertions and ordinary documentation review do not constitute instrumented bench/HIL, loaded-frame, installed-site or qualified physical-safety review. #59, #67, #76, #78 and #79 carry the implementation/evidence follow-ups.

Test-record minimum

Every committed evidence record should include:

  • test identifier, purpose, linked requirement/issue, and date;
  • part/assembly/build/software/configuration revisions;
  • setup diagram or photos safe for public release;
  • environmental and initial conditions;
  • calibrated instruments and measurement uncertainty where relevant;
  • exact procedure and stop conditions;
  • raw data location and analysis version;
  • result against predefined acceptance criteria;
  • anomalies, damage, follow-up, and reviewer.
  • applicable LS requirement IDs, authorized stage/rig scope, measured fault-detection/response times, stopping distance/force and line-clearance results where relevant, and any evidence still missing before the next stage.

Do not replace raw data with a screenshot when machine-readable measurements exist.

Commissioning rules

  • Begin at reduced speed, acceleration, force/current, workspace, and access.
  • Validate one hazard/control at a time when practical.
  • Keep people outside loaded and moving envelopes.
  • Stop on unexpected noise, motion, heat, smell, deformation, line damage, low clearance, moisture, or sensor disagreement.
  • Never bypass a safeguard just to finish a test.
  • After any structural, electrical, line, drum, pod, dock, firmware, or calibration change, rerun affected acceptance tests.
  • Simulation may predict tests but cannot authorize a higher hardware limit.

Open engineering questions carried into testing

  • Final post and anchor design for the real soil/wind environment.
  • Final pulley and drum size.
  • Maximum line tension, speed, acceleration, and parking tension.
  • Powered-line conductor and slip-ring life.
  • Converter/servo selection, pod mass, and settling interval.
  • Need for IMU, tension sensing, controlled lighting, differential signals, and fail-safe brakes.
  • Final dock geometry and power-loss response.
  • Final per-bed/plant mapping and fiducial system.