Packaging proposal r0.1.0 — concept-unvalidated, 9 October 2026. This adds a reviewable physical arrangement to the cabinet baseline. It does not select an enclosure SKU, change power-supply allocation, or establish an electrical construction schedule. The two supplies remain separate outputs; their allocation and return/bonding arrangement require electrical review.

Envelope and views

The reference uses 500 mm width × 600 mm height × 250 mm depth. The existing catalog's approximately 400 × 300 × 200 mm starting cabinet remains a procurement starting point. The larger proposal reserves space for protection, routing, service access and a separate edge computer alongside the two supplies. It is not proof that either size fits the delivered hardware. Compare usable internal dimensions, door/contact depth, mounting plate, cable bends, cooling and final devices before selecting or revising the catalog item.

The canonical assembly source uses X across the cabinet, Y toward its rear and Z upward. The floor is Z=0; the front is Y=-125 and the rear is Y=125. Its nominal 460 × 560 × 2 mm mounting plate is centred at Y=105. The source's assumed 3 mm shell and 4 mm door are visualization geometry, not construction or ingress specifications.

  • Default service view: door opened 105°; supplies and controls visible.
  • Closed view: door_angle=0.
  • Exploded service illustration: explode=1; offsets identify inspection groups and do not prescribe removal paths or cable slack.
  • Website: selectable constituent meshes, orbit/zoom and the same exploded offsets exported from the assembly source.

The shell/door are proposed context linked to the enclosure BOM item. The six other purchased part types reuse their individual CAD modules, including two instances of the supply. Protection-device solids are generic occupied-space envelopes; open frames represent unselected stop-interface and edge-computer reserves. No reference component is a printable part or adds a purchase line.

Arrangement

Area Nominal position / occupied space Purpose and unresolved work
Mains row DIN-rail centre Z=535; isolator 54, RCBO 36 and surge-device 54 mm widths; each 85 mm high × 60 mm deep Separate mains entry/isolation/protection; device types, coordination, ratings and terminal geometry unselected
Protective-earth bar Upper right, Z=535; 95 × 12 × 8 mm proxy Protective conductor termination and enclosure/door bonding; material, connections and conductor sizes unselected
Supplies X=-92/+92, Z=380; each 121 mm wide × 215 mm high × 50 mm deep in the reference mesh, including its terminal lip Two existing supply references, rotated vertically; manufacturer's mounting orientation, spacing and cooling requirements must supersede this pose
DC protection row DIN-rail centre Z=225; five 18 mm branch envelopes Space for four motor branches and one pod branch; actual fuse/holder sizes, controller protection and supply grouping unresolved
Independent stop interface Lower right of DC row; 85 × 85 × 65 mm open reserve Reviewed hardwired stopping/supervision devices; no safety relay, contactor or circuit selected
Motion control Terminal-board centre X=-95, Z=115; 90 × 83 × 19.5 mm reference including terminal/rail proxies; Pico stacked 18 mm forward Header/connector keep-outs, support heights, mounting holes and wiring access require received-unit measurements
Controller converter and signal ground Converter centre X=−150, Z=55; 50 × 30 × 17 mm Received 5 V converter, four Ø3 mm holes at 45 × 24 mm pitch; four 7 mm insulating sleeves and nominal M2.5 × 16 stacks through the 2 mm plate. Receipt/mounting record. Signal-return block remains separate from protective earth
Edge-computer reserve X=100, Z=115; 140 × 110 × 55 mm open reserve Provisional occupied space only; host, mounts, supply, cooling, network and recovery access unselected
Field terminals Lower front, Z=35 Generic power/control terminal envelopes; terminal count, separation, wire sizes and shields unresolved
Wiring ducts 28 mm wide × 35 mm deep side channels Routing placeholders; actual duct capacity and mains/control segregation unresolved
Cable entries Six illustrative bottom collars Visual entry positions only; not the required cable count, gland selection or drilling pattern
Door Left hinge; emergency-stop operator near outer edge Accessibility, door swing, hinge/lock, protective bonding and a retained flexible harness require review

The 5 mm nominal vertical gap between the supply envelopes and upper protective devices is only a geometric gap. It is not a qualified electrical clearance, ventilation allowance or service space. The final manufacturer's spacing may require a larger enclosure or different arrangement.

Power and control interfaces

These identifiers name interfaces for design discussion. They are not physical terminal numbers; a reviewed terminal schedule must define the final blocks, pins, conductor identification and schematic cross-references.

Logical interface Destination / function Information needed before implementation
AC-IN Fixed-site mains feed Source protection, isolator, RCD/RCBO, surge approach, conductor and entry specification
PE Protective earthing and bonding Supply PE, enclosure/door continuity, site earth arrangement and inspection records
DC-A / DC-B Two separate 48 V supply outputs Exact supply models, load allocation, startup/inrush, fault coordination and return/bonding scheme
MOTOR-A…D Four locally protected 48 V motor-driver feeds Per-branch current, conductor length/section, voltage drop, fusing, isolation and pole endpoints
POD-48 Protected powered-line supply at one pole Separate isolation, worst-load drop, slip-ring/line limits and reviewed stop-state behavior
CTRL-5 Converter → Pico / cabinet auxiliaries Converter input/transient margin, current, local protection and brownout/reset behavior
STEP/DIR-A…D Pico → four pole-mounted CL57Y-V20 drivers Existing GP2…GP9 assignment; input compatibility, cable lengths, EMI and false-step tests
SIGNAL-GND Dedicated STEP/DIR pair returns Signal-return routing and reviewed relationship to power returns / PE; no assumed equivalence
HOME / LIMIT / ALARM / ENABLE Local motion/safety endpoints Instrumentation, independent limits and final electrical/GPIO allocation; reserved pairs imply no circuit
E-STOP Door operator → independent stop path Contacts, supervision, reset, output states, energy isolation and restraint sequence
EDGE↔PICO Dedicated wired cabinet link USB/isolated serial decision, framing, authentication, reset effects and connector access
EDGE↔POD / WAN Imaging jobs, cached images and cloud connectivity LAN/router hardware, antenna/ports, local diagnostics and offline recovery

Four CL57Y-V20 drivers stay at the poles with their short motor/encoder harnesses. The camera Pi remains on the pod. The separate cabinet edge machine follows ADR-0008: Debian 13/systemd target, two CPU cores, 4 GiB RAM and at least 64 GiB storage as starting budgets. The reserve drawn here does not establish that a suitable host fits.

Cabinet BOM completion register

The canonical cabinet assembly currently contains one enclosure, two supplies, one Pico, one expansion board, one controller converter, one signal-ground block and one emergency-stop button: seven part types, eight purchased units. Supplies are sourced through the motor-kit bundle. The known-goods figure is a partial allocation, not a complete installed cabinet price.

Missing or unselected group Selection record to add
Final enclosure / mounting plate / wall mounts Manufacturer, usable dimensions, environment, mounting, door swing and service access
DIN rails, ducts, end stops and fixings Dimensions, quantities, conductor capacity and usable plate layout
Mains protection and isolation Reviewed schematic, selected isolator/RCD/RCBO/surge devices, coordination and installation assumptions
Protective-earth terminals and bonding Exact bars/terminals, enclosure/door bonds and test access
DC protection and distribution Fuse/holder/terminal IDs, branch grouping, fault rating, controller and pod isolation
Independent stop/supervision hardware Devices and circuit selected by the local safety design; button alone is incomplete
Field terminals, connectors and glands Count by actual cable, conductor range, entry diameter, weather/service requirements
Internal conductors and identification Wire specification, ferrules, labels, schematic references and revision plate
Edge computer and networking Selected host/storage, DC conversion, network hardware, thermal budget and recovery interface
Condensation / thermal treatment Measured losses and environment; qualified ventilation, heater or other treatment if required

Add normalized BOM identities/usages and dated supplier offers when selections exist; do not create priced purchase lines from these reference envelopes.

Assembly and service planning

The proposed sequence is enclosure/plate/mounts, rails and ducts, protective bonding, reviewed protection/distribution, supplies, control electronics, then field terminations and labels. Keep mounting patterns parametric until selected hardware is measured. The stop operator needs serviceable door wiring and bonding; neither harness is modeled as an accepted installation.

Before commissioning, reconcile every physical label with the as-built schematic and terminal schedule. Verify the qualified electrical inspection, branch fault and isolation tests, worst-duty enclosure temperatures, field signal integrity, controller brownout/watchdog behavior, independent stopping and power-loss restraint described in the cabinet acceptance requirements.

The CAD reference and website demonstrate nominal source geometry and navigation only. They do not establish received-hardware fit, IP rating, thermal capacity, electrical safety, safe stopping or installed operation.